CELEC-EP ELECTROGUAYAS selected GENESYS to provide mobilization, installation and startup of their 174 MVA transformer for the Trinitaria 130MW-SB Thermoelectric Power Plant.

April 29, 2011 at 11:33 am | Commisioning, News, Power Tech | Sin comentarios

 

The project was performed under emergency conditions and executed in 30 days from equipment reception in Houston to Startup. GENESYS performed the works with “cero” safety incidents and 14 days ahead of schedule.

Transportation of Transformer and equipment from Abilene to Port of Houston.

Transportation of equipment from the Port of Guayaquil to the Trinitaria Power Station.

Construction, erection and testing of the 177MW 138/13.8KV Transformer.

Commissioning & Start up of the bay